Work
completed last week, May 23rd to May 27th:
·
Concrete
poured from new sidewalk to curb on west side of Tower Drive from Aviator Lane
to Valor Drive
·
Pour
concrete planter beds along the west side of Tower Drive from Aviator Lane to
Valor Drive
o
All
planter beds are now complete along west side of Tower Drive
·
Contractor
is preparing sections where stamped and colored concrete will be installed
·
Electrical
conduit, foundations, and hand-holes installed along project site
·
Irrigation piping
installation on-going
Work to be completed
May 31st to June 3rd:
·
Concrete
poured from new sidewalk to curb on west side of Tower Drive from Wolverine
Drive to Valor Drive
o
It
is anticipated all standard concrete along the west side of Tower Drive will be
completed by the end of the week!
·
Concrete
sidewalk installation along Navy Boulevard
·
Begin
installation of stamped and colored concrete on west side of Tower Drive
·
North
side of Aviator from Tower (east) to Patriot: Begin sidewalk and ramp/staircase
removal. The doors to Ra Sushi on Aviator Drive will be closed; customers will
gain access to Ra Sushi using the patio doors located on Patriot Boulevard
o
Sidewalk
on the north side of Aviator will also be closed. Pedestrians will be rerouted
to use the sidewalk along the south side of Aviator Drive
·
Electrical
conduits, foundations, and hand-hole construction continues
·
Irrigation
piping installation continues
Week of June 6th – Work shifts to EAST side of Tower Drive
It is anticipated the contractor will move to the east side of Tower Drive from Navy
Boulevard to Aviator Lane starting Monday, June 6th. This will be a
significant project milestone as a majority of the work on the west side of
Tower Drive will be completed.
The shifting to east side of the Tower Drive will also mean
the businesses along this side of the street will be directly affected.
It is anticipated concrete sidewalk removal will begin on
Monday, June 6th. Concrete sidewalk installation adjacent to the
buildings will occur the same week during the late afternoon and evening hours.
Businesses will be contacted individually regarding timing of the work to be
completed, temporary access following the concrete sidewalk removal, and
restrictions to doorways during concrete sidewalk installation.
Saturday Work
Due to the construction schedules and completion timeframes,
the contractor will begin working most Saturdays following the Memorial
Day Weekend. The contractor has been granted permission by Village staff to
begin work at 8:00 AM on Saturdays to avoid the busiest times of the day. The
contractor anticipates being completed with their work by 3:00 PM.