Friday, July 29, 2016

Construction Crews Prepare for Glenview’s Art Fest

Construction crews have been working to restore sidewalk in the Glen Town Center where it was previously removed in preparation for Glenview’s Art Fest starting in August 6th.

Work completed this week, July 25 to July 29:
  • Poured white concrete on Tower Drive between Navy Boulevard and Valor Drive 
  • Completed installation of planter beds on Valor Drive between Tower Drive and Patriot Boulevard
  • Poured sidewalk and select driveways into parking garage on north Sable Drive 
  • Sidewalk prepped for concrete pour on Valor Drive between Tower Drive and Patriot Boulevard 
Construction activity scheduled for next week, beginning August 1:
  • Seal stamped, colored concrete on Tower Drive between Navy Boulevard and Valor Drive
  • Pour stamped, colored concrete on Tower Drive between Navy Boulevard and Valor Drive
  • Pour concrete sidewalk on Valor Drive between Tower Drive and Patriot Boulevard 
  • Remove and replace curb, install planter beds, and prepare and pour concrete sidewalk on north Wolverine Drive between Tower Drive and the parking garage
  • Finish pouring concrete driveways into parking garage on north Sable Drive
  • Clean and prepare for Glenview's Art Fest (August 6-7)
Future Construction Activities:
  • Begin removal on south Wolverine Drive between Tower Drive and the parking garage
  • Begin removal of existing sidewalk on Navy Boulevard by the intersection of Navy Boulevard and Patriot Boulevard
Friendly Reminder:
  • Glenview's Art Fest starts on August 6 and goes through August 7. Preparation for Art Fest will begin on Friday, August 5. 
  • All businesses are open during construction!
  • Surface parking spots are limited. Parking in garages is strongly encouraged. 

Friday, July 22, 2016

Construction Continues on Tower Drive from Navy Blvd to Valor Drive

Work completed this week, July 18th to July
  • Removed and replaced vandalized concrete sidewalk along Valor Drive and Tower Drive
  • Removed and replaced driveways to parking garages on north side of Sable Drive
  • Poured concrete curb & gutter along Tower Drive
  • Removed remaining sidewalk along Valor Drive east of Tower Drive
  • Excavated for planter beds
  • Installed concrete curbing around planter beds on Tower Drive and Valor Drive
  • Removed concrete sidewalk along north side of Wolverine Drive
  • Installed electrical conduit and lighting accessories along Sable Drive, Wolverine Drive, Tower Drive, and Valor Drive
  • Installed irrigation conduits along Sable Drive, Wolverine Drive, Tower Drive, and Valor Drive
  • Began installing irrigation piping and spray heads along Tower Drive
Construction activity scheduled for next week, July 25th to July 29th  
  • Pour remaining concrete sidewalk along Tower Drive from Navy Blvd to Valor Drive
  • Pour remaining concrete sidewalk along Valor Drive
  • Pour stamped and colored concrete along Tower Drive and Valor Drive
  • Install irrigation conduits along Sable Drive, Wolverine Drive, Tower Drive, and Valor Drive
  • Install electrical conduit and lighting accessories along Sable Drive, Wolverine Drive, Tower Drive, and Valor Drive

Anticipated work in future weeks:
  • Prior to Arts Festival on August 5th
    • All concrete sidewalk previously removed will be replaced along Tower Drive, Valor Drive, Sable Drive, and Wolverine Drive
  • Early September
    • Landscape restoration with new trees and perennials in the planting beds - due to more favorable growing conditions
 
Friendly Reminder:
  • All businesses are open during construction!
  • Surface parking spots are limited. Parking in garages is strongly encouraged.
 

Friday, July 15, 2016

Work along Tower Drive Between Navy Blvd and Valor Drive Continues

Work completed this week, July 11th to July 15th   
·         Sidewalk removal on the east side of Tower Drive from Valor Drive to Navy Blvd.
·         Prep and pour sidewalk adjacent to the buildings on the east side of Tower Drive from Valor Drive to Navy Blvd
·         Prep and pour concrete sidewalk and driveways at the following locations:
o   South side of Valor Drive east of Tower Drive
o   North side of Sable Drive
o   Tower Drive in front of Eggsperience
o   Tower Drive access to rear parking garage
·         Removed and poured required curb & gutter along Tower Drive from Valor Drive to Navy Blvd.
·         Sealed previously installed stamped and colored concrete
·         Install electrical conduit and lighting accessories on the north side of Sable Drive
·         Install irrigation conduits on the north side of Sable Drive

Construction activity scheduled for next week, July 18th to July 22nd
·         Remove and replace vandalized concrete sidewalk along Valor Drive and Tower Drive
·         Remove and replace driveways to parking garages on north side of Sable Drive
·         Pour concrete curb & gutter along Tower Drive
·         Remove remaining sidewalk along Valor Drive east of Tower Drive
·         Excavate for planter beds
·         Install concrete curbing around planter beds on Tower Drive and Valor Drive
·         Remove concrete sidewalk along north side of Wolverine Drive
·         Install electrical conduit and lighting accessories along Sable Drive, Wolverine Drive, Tower Drive, and Valor Drive
·         Install irrigation conduits along Sable Drive, Wolverine Drive, Tower Drive, and Valor Drive
·         Begin installing irrigation piping and spray heads along Tower Drive
Anticipated work in future weeks:
·         Week of July 25th
o   Pour remaining concrete sidewalk along Tower Drive from Navy Blvd to Valor Drive
o   Pour remaining concrete sidewalk along Valor Drive
o   Pour stamped and colored concrete along Valor Drive and Tower Drive.
·         Prior to Arts Festival on August 5th
o   All concrete sidewalk previously removed will be replaced along Tower Drive, Valor Drive, Sable Drive, and Wolverine Drive
·         Early September
o   Landscape restoration with new trees and perennials in the planting beds.
o   Due to more favorable growing conditions

This past week had a few unfortunate circumstances that caused some significant issues for businesses throughout the project area. On Friday, July 15th, power was lost for an extended period of time for all businesses along the west side of Tower Drive. The exact cause for the power outage is still being determined. The major priority at this point is to get power restored as quickly as possible. We understand the major affect this had on all the businesses in the area and will continue to work to determine the cause for the outage.

 Also, sections of newly poured concrete sidewalk along Tower Drive and Valor Drive were damaged due to some unfortunate circumstances. Several sections of concrete were vandalized prior to the concrete setting and similarly several sections were exposed to unexpected weather conditions. These areas of sidewalk will need to be removed and replaced. The contractor anticipates to complete this work next week. The businesses affected by this additional work will be notified prior to the work beginning.

Friendly Reminder:
·         All businesses are open during construction!
·         Surface parking spots are limited. Parking in garages is strongly encouraged.

Friday, July 8, 2016

Work along Tower Drive Between Navy Blvd. and Valor Drive Begins


Work completed this week, July 2nd  to July 9th  

·         Removed existing retaining wall on south side of Valor Drive east of Tower Drive
·         Installed new retaining wall on north side of Valor Drive east of Tower Drive
o   Businesses will be provided temporary access during construction. Thank you for your patience and understanding. We will continue to do everything possible to ensure access is provided throughout the day.
·         Concrete sidewalk removal along north side of Sable Drive
·         Concrete curb and gutter removal and replacement along the north side of Sable Drive

Construction activity scheduled for next week, July 11th to July 15th  

·         Sidewalk removal on the east side of Tower Drive from Valor Drive to Navy Blvd.
o   This will be the last significant stage of sidewalk removal along Tower Drive
·         Prep and pour sidewalk adjacent to the buildings on the east side of Tower Drive from Valor Drive to Navy Blvd
·         Late afternoon / early evening work, including concrete pouring, scheduled for Monday through Wednesday
·         Remove required curb & gutter along Tower Drive from Valor Drive to Navy Blvd.
·         Prep and pour concrete sidewalk on the south side of Valor Drive east of Tower Drive, the north side of Sable Drive and on Tower Drive in front of Eggsperience
·         Install electrical conduit and lighting accessories on the north side of Sable Drive
·         Install irrigation conduits on the north side of Sable Drive


Anticipated work in future weeks:

·         Week of July 18th
o   Removal and pouring of concrete sidewalk on the north and south side of Navy Blvd in front of Bravo and Jameson’s Steakhouse
o   Removal and pouring of concrete sidewalk on the south side of Wolverine Drive
o   Potentially pour sidewalk from sidewalk previously installed to curb & gutter
·         Early September
o   Landscape restoration with new trees and perennials in the planting beds
o   Due to more favorable growing conditions
 
Friendly Reminder:

·         All businesses are open during construction!
·         Surface parking spots are limited. Parking in garages is strongly encouraged.

Friday, July 1, 2016

Concrete Work on East Side of Tower from Aviator Lane to Navy Blvd. Completed

Work completed this week, June 24th to July 1st
·         Installed colored and stamped concrete on east side of Tower Drive from Navy Blvd. to Aviator Lane
·         Installed colored and stamped concrete in a few miscellaneous areas previously not installed
·         Installed concrete sidewalk on south side of Sable Drive
o   Including Von Maur entrance
·         Installed concrete sidewalk along Aviator Lane, east of Tower Drive on lower level of retaining wall
·         Install concrete sidewalk at miscellaneous locations along the project site that were previously removed.
o   South east corner of Aviator Lane and Tower Drive, within South Park Area
o   South east corner of Navy Blvd and Tower Drive, near State & Main Bar & Grill
o   Miscellaneous areas along Navy Blvd
·         Installed topsoil in planter beds
·         Asphalt patching in front of previously replaced concrete curb & gutter
·         Continued with installation of irrigation piping.
·         Continued with installation of electrical conduit and wiring for street lighting and accent lights.
·         Perform general site clean-up in preparation for July 4th Holiday
o   Install temporary stone within areas of concrete sidewalk that were not poured
o   Swept project site
o   Removed unnecessary barricades and fencing
o   Removed stockpiles and debris
·         All outdoor seating along Tower Drive is accessible during the July 4th Holiday
o   East side of Tower Drive from Aviator Lane to Navy Blvd – Remaining orange construction fencing removed
o   East side of Tower Drive from Navy Blvd to Valor Drive – Existing sidewalk still in-place
o   West Side of Tower Drive – Patio seating has been available for several weeks

Construction activity scheduled for next week, July 4th to July 8th  
·         No work on-site July 4th Weekend
·         Remove existing retaining wall on north side of Valor Drive east of Tower Drive
·         Install new retaining wall on north side of Valor Drive east of Tower Drive
o   Businesses will be provided temporary access during construction. Thank you in advance for your patience and understanding. We will do everything possible to ensure access is provided throughout the day.
·         Concrete sidewalk removal and replacement along north side of Sable Drive

Anticipated work in future weeks:
·         Week of July 11th
o   Removal and pouring of concrete sidewalk adjacent to the buildings on the east side of Tower Drive from Valor Drive to Navy Blvd
§  This will be the final major phase of concrete removal and replacement for the project.
§  Anticipate to complete this section of streetscape prior to Arts Festival on August 5th
o   Removal and pouring of concrete sidewalk on northwest corner of Tower Drive and Sable Drive, near Eggsperience.
·         Early September
o   Landscape restoration with new trees and perennials in the planting beds.
o   Due to move favorable growing conditions

Friendly Reminder:
·         No work will be performed over July 4th Holiday Weekend!!!
·         All businesses are open during construction!
·         Surface parking spots are limited. Parking in garages is strongly encouraged.
Have a safe and enjoyable July 4th Holiday Weekend!!!!