Completed removal of concrete sidewalk from new
sidewalk to curb & gutter on east side of Tower Drive from Aviator to Navy
Blvd.
o
Installation of aggregate base course, final
grading, setting forms, and installing reinforcement in preparation for
concrete pouring
·
Poured colored and stamped concrete along Navy
Blvd. and along Tower Drive at Sable Drive
o
All concrete previously removed along Navy Blvd
is now replaced
·
Poured concrete sidewalk at intersections of
Tower Drive and Wolverine Drive, Tower Drive and Sable Drive, Tower Drive and
Sable Drive
·
Poured concrete curb & gutter on east side
of Tower Drive from Aviator Drive to Navy Blvd.
·
Poured concrete curbing around planter beds
along the east side of Tower Drive between Aviator Drive and Navy Blvd.
·
Poured Concrete steps and top sidewalk on north
side of Aviator Drive, east of Tower Drive
o
RA Sushi main doors re-opened on Tuesday!!!!
·
Removed concrete sidewalk on south side of Sable
Drive in front of Von Maur
·
Irrigation piping installation
·
Electrical conduit and wiring installation for
street lighting and accent lights.
o
Electrical conduit, wiring, and connections
completed for street lights on West side of Tower Drive
o
Electrical conduit, wiring, and connections
completed for street lights on East side of Tower Drive from Aviator to Navy
Blvd
Construction
activity scheduled for next week, beginning June 20th
·
Complete concrete curbing around planter beds on
east side of Tower Drive from Navy Blvd. to Aviator
·
Pour concrete sidewalk from previously installed
sidewalk to curb & gutter on east side of Tower Drive from Navy Blvd. to
Aviator
·
Depending on work progress, begin installing
colored and stamped concrete on east side of Tower Drive from Navy Blvd. to
Aviator
·
Continue with installation of irrigation piping
·
Continue with installation of electrical conduit
and wiring for street lighting and accent lights.
Anticipated work in future weeks:
·
Week of June 27th
o
Complete stamped and colored concrete along east
side of Tower Drive from Navy Blvd to Aviator
o
Pour concrete sidewalk along south side of Sable
Drive
o
Goal by end of the week: All concrete that was
previously removed will be replaced with new concrete in anticipation of July 4th
Holiday
·
Week of July 4th
o
No work performed on Monday, July 4th
o
Concrete removal and pouring along north side of
Sable Drive and along one side of Wolverine Drive
o
Removal and replacement of existing retaining
wall along north side of Valor Drive
·
Week of July 11th
o
Removal and pouring of concrete sidewalk
adjacent to the buildings on the east side of Tower Drive from Valor Drive to
Navy Blvd
§
This will be the final major phase of concrete
removal and replacement for the project.
Friendly
Reminder:
·
All businesses are open during construction!
·
Surface parking spots are limited. Parking in
garages is strongly encouraged.
·
Saturday work continues – the contractor has
been granted permission by Village staff to begin work at 8:00 AM on Saturdays
to avoid the busiest time of the day. The contractor anticipates being
completed with their work by 3:00 PM