·
Concrete
sidewalk installation along west side of Tower Drive
o
A
majority of the standard concrete sidewalk on the west side of Tower Drive is
completed.
o
Primary
locations remaining include the intersections of Wolverine Drive, Sable Drive,
and Valor Drive
·
Concrete
sidewalk installation along Navy Boulevard
·
Stamped
and colored concrete sidewalk along west side of Tower Drive
o
A
majority of the colored and stamped concrete on the west side of Tower Drive is
completed with the exception of a few areas where additional work still needs
to be completed.
·
Removal
of sidewalk and ramp/staircase removal along north side of Aviator from Tower
to Patriot Boulevard
·
Began construction
of retaining wall along the north side of Aviator from Tower to Patriot
Boulevard
o
Doors
to RA Sushi along Aviator Drive are closed due to construction.
o
Access
to RA Sushi is available through patio doors off of Patriot Boulevard
o
Sidewalk
along north side of Aviator is closed, please use sidewalk on south side of
street
·
Electrical
conduits, foundations, hand-holes, and pulling of electrical wires continues
·
Irrigation piping installation on-going
The orange construction fence along
the west side of Tower Drive has largely been removed now that the majority of
the concrete sidewalk and stamped and colored sidewalk is completed. As the
remaining concrete sidewalk is completed, more of the temporary ramps and
orange fencing will be removed to provide pedestrian access.
Thank you to all the businesses along
the west side of Tower Drive for your patience and understanding during the
construction process on that side of the street.
Work to be completed June 6th to June 10th
·
Concrete sidewalk removal along EAST side of
Tower Drive from Navy Boulevard to Aviator Lane
o
Adjacent to buildings
o
Temporary access will be provided to all doors
following concrete sidewalk removal
·
Pour concrete sidewalk along EAST side of Tower
Drive from Navy Boulevard to Aviator Lane
o
Adjacent to buildings approximately 8 feet
o
Work scheduled to be begin during late afternoon
and early evening hours of Tuesday June 7th and Wednesday, June 8th
and will be completed as soon as possible.
o
Individual businesses will be coordinated with
to determine restricted access to doorways
·
Begin removal of concrete sidewalk from
installed concrete to concrete curb & gutter on EAST side of Tower Drive
from Navy Boulevard to Aviator Lane.
·
Concrete sidewalk on west side of Tower Drive
near intersections of Wolverine Drive and Sable Drive.
·
Complete construction of retaining wall along
north side of Aviator Lane between Tower Drive and Patriot Boulevard
·
Concrete sidewalk and steps on north side of
Aviator
·
Continued electrical installations of conduits,
foundations, hand-holes, and wiring on west side of Tower Drive
·
Continue irrigation piping installation on west
side of Tower Drive
We understand the inconvenience this construction project
causes to those business directly adjacent to the work being performed,
residents living in the neighborhood, and businesses within the entire Glen
Town Center. Please understand the Village will do everything possible to
minimize these inconveniences to the greatest extent possible. Your cooperation
and understanding is greatly appreciated.
Saturday Work
Due to the construction schedules and completion timeframes,
the contractor will begin working most Saturdays. The contractor has been
granted permission by Village staff to begin work at 8:00 AM on Saturdays to
avoid the busiest times of the day. The contractor anticipates being completed
with their work by 3:00 PM.