Work on East Side of Tower Expected to Be Completed prior to July 4th Holiday

Work completed this week, June 20th to June 24th:
·         Completed concrete curbing around planter beds on east side of Tower Drive from Navy Blvd. to Aviator Lane
·         Poured concrete sidewalk from previously installed sidewalk to curb & gutter on east side of Tower Drive from Navy Blvd. to Aviator Lane
·         Continued with installation of irrigation piping
·         Continued with installation of electrical conduit and wiring for street lighting and accent lights.

Construction activity scheduled for next week, June 27th to July 1st
·         Install colored and stamped concrete on east side of Tower Drive from Navy Blvd. to Aviator Lane
·         Install concrete sidewalk on south side of Sable Drive
·         Install sidewalk along Aviator Lane, east of Tower Drive on lower level of retaining wall
·         Install concrete sidewalk at miscellaneous locations along the project site that were previously removed.
·         Continue with installation of irrigation piping.
·         Continue with installation of electrical conduit and wiring for street lighting and accent lights.
·         Perform general site clean-up in preparation for July 4th Holiday
·         Allow outdoor patio seating areas to be opened prior to July 4th Holiday along east side of Tower Drive.
GOAL for Week: Install concrete in all areas that were previously removed prior to July 4th Holiday.

Anticipated work in future weeks:
·         Week of July 4th
o   No work performed on Monday, July 4th
o   Concrete removal and pouring along north side of Sable Drive
o   Removal and replacement of existing retaining wall along north side of Valor Drive
§  Businesses will be provided temporary access during construction. Thank you in advance for your patience and understanding. We will do everything possible to ensure access is provided throughout the day.
·         Week of July 11th
o   Removal and pouring of concrete sidewalk adjacent to the buildings on the east side of Tower Drive from Valor Drive to Navy Blvd
§  This will be the final major phase of concrete removal and replacement for the project.
§  Anticipate to complete this section of streetscape prior to Arts Festival on August 5th
o   Removal and pouring of concrete sidewalk on northwest corner of Tower Drive and Sable Drive, near Eggsperience.

Friendly Reminder:
·         No work will be performed over July 4th Holiday Weekend!!!
·         All businesses are open during construction!
·         Surface parking spots are limited. Parking in garages is strongly encouraged.
·         Saturday work continues – the contractor has been granted permission by Village staff to begin work at 8:00 AM on Saturdays to avoid the busiest time of the day. The contractor anticipates being completed with their work by 3:00 PM