The concrete work throughout the project site is complete as we are approach the final phase of the project. We greatly appreciate everyone’s patience throughout this project. Please note, surface parking spots will continue to be limited in anticipation for landscape work, delivery and installation of outdoor furniture and décor, and continued electrical work.

Work completed this week, August 15 to August 19:
  • Completed pouring concrete throughout the project site.
  • Finished installing planter beds on Navy Boulevard.
  • Installed topsoil in planter beds to prepare for landscape work.
  • Ongoing electrical and irrigation work.
Construction activity scheduled for next week, beginning August 22:
  • Install railing at the retaining wall on Aviator Drive.
  • Finish installing irrigation system and electrical throughout project site.
  • Begin landscape work – installation of trees and shrubs.
  • Install outdoor furniture including trash cans and benches.
  • Finalize repairs on retaining walls on Valor Drive and Aviator Drive.
  • Seal stamped, colored concrete throughout project site.
  • Finish caulking along buildings, doorways will be caulked after business hours.
Friendly Reminder:
  • Parking on surface spots throughout the Glen Town Center as landscape and outdoor furniture is delivered and installed. Parking in garages in strongly encouraged. 
  • All businesses are open during construction!