Completed concrete curbing around planter beds
on east side of Tower Drive from Navy Blvd. to Aviator Lane
·
Poured concrete sidewalk from previously
installed sidewalk to curb & gutter on east side of Tower Drive from Navy
Blvd. to Aviator Lane
·
Continued with installation of irrigation piping
·
Continued with installation of electrical
conduit and wiring for street lighting and accent lights.
Construction activity scheduled for next week, June 27th to July 1st
·
Install colored and stamped concrete on east
side of Tower Drive from Navy Blvd. to Aviator Lane
·
Install concrete sidewalk on south side of Sable
Drive
·
Install sidewalk along Aviator Lane, east of
Tower Drive on lower level of retaining wall
·
Install concrete sidewalk at miscellaneous
locations along the project site that were previously removed.
·
Continue with installation of irrigation piping.
·
Continue with installation of electrical conduit
and wiring for street lighting and accent lights.
·
Perform general site clean-up in preparation for
July 4th Holiday
·
Allow outdoor patio seating areas to be opened
prior to July 4th Holiday along east side of Tower Drive.
GOAL for Week: Install concrete in all areas that were previously
removed prior to July 4th Holiday.
Anticipated work in future weeks:
·
Week of July 4th
o
No work performed on Monday, July 4th
o
Concrete removal and pouring along north side of
Sable Drive
o
Removal and replacement of existing retaining
wall along north side of Valor Drive
§
Businesses will be provided temporary access
during construction. Thank you in advance for your patience and understanding.
We will do everything possible to ensure access is provided throughout the day.
·
Week of July 11th
o
Removal and pouring of concrete sidewalk
adjacent to the buildings on the east side of Tower Drive from Valor Drive to
Navy Blvd
§
This will be the final major phase of concrete
removal and replacement for the project.
§
Anticipate to complete this section of
streetscape prior to Arts Festival on August 5th
o
Removal and pouring of concrete sidewalk on
northwest corner of Tower Drive and Sable Drive, near Eggsperience.
Friendly
Reminder:
·
No work will be performed over July 4th
Holiday Weekend!!!
·
All businesses are open during construction!
·
Surface parking spots are limited. Parking in
garages is strongly encouraged.
·
Saturday work continues – the contractor has
been granted permission by Village staff to begin work at 8:00 AM on Saturdays
to avoid the busiest time of the day. The contractor anticipates being
completed with their work by 3:00 PM