Friday, April 1, 2016

Concrete Sidewalk Pouring on West Side of Tower Drive Scheduled for This Week

Construction Completed last Week of March 28 – April 1:
·         Removed existing concrete sidewalk adjacent to building on the West side of Tower Drive from Aviator Lane to Valor Drive. (Zone 1 and Zone 2)
·         Installed temporary ramps to businesses.
·         Graded and installed base course, set forms, installed reinforcement, and prepared for concrete pour
·         Concrete pouring was cancelled this week due to rain in the forecast on Wednesday and Thursday.  

Upcoming Work Anticipated for Next Week, April 4 – April 8:  

Concrete pouring scheduled for last week has been rescheduled due to rainy weather conditions. 

Zone 1 (West side of Tower Drive from Aviator Lane to Navy Boulevard)
Businesses within zone include: Curragh, Flight, Mingle Juice Bar, Potbelly’s, ArcLight Theaters, Ben & Jerry’s Ice Cream, The Candy Crossing, Yard House, Dick’s Sporting Goods, Ulta, Carter’s, Justice 

Monday (4/4) thru Tuesday (4/5)
·         Pour concrete sidewalk adjacent to buildings starting in late afternoon / early evening
o   Pedestrian access will be allowed on sidewalks at start of business the morning following concrete pour
·         Loudest noise anticipated during concrete pouring: back-up alarms of concrete trucks
·         Access to businesses will be coordinated individually  

Zone 2 (West side of Tower Drive from Navy Boulevard to Valor Drive)
Businesses within zone include: Von Maur, Glenview Jewelers, Wet Nose, Skin Deep, Gordon Salon, Eggsperience, Glen Town Center Management Office, Funtopia 

Monday (4/4) thru Tuesday (4/5)
·         Installation and grading of new aggregate base course
·         Installation of concrete forms for concrete sidewalk
·         Installation of reinforcement along buildings 

Wednesday (4/6) thru Friday (4/8)
·         Pour concrete sidewalk adjacent to buildings starting in late afternoon / early evening
o   Pedestrian access will be allowed on sidewalks at start of business the morning following concrete pour
·         Loudest noise anticipated during concrete pouring: back-up alarms of concrete trucks
·         Access to businesses with be coordinated individually 

Sable Drive: South side of roadway from Tower Drive to west end:
Business affected: Von Maur 

Monday (4/4) thru Tuesday (4/5)
·         Remove existing concrete sidewalk from building to curb line
o   Concrete in front of doors to Von Maur will be left in place at this time
·         Installation and grading of new aggregate base course
·         Installation of concrete forms for concrete sidewalk
·         Installation of reinforcement along buildings 

Zone 3 (South side of Navy Blvd from Patriot Blvd to Tower Drive & East Side of Tower Drive from Navy Blvd to Aviator Drive)
Businesses affected: Pigtails & Crewcuts, Evereve, Stella 315, Starbucks, Vintage Nest, Ella Louvi Retail Therapy, Dino’s Sports Fan Shop, Assure Vision, Gadget Works, GameStop, Rocket Fizz, Color Me Mine, Forever Yogurt, Noodles & Company, Montira Thai Restaurant, Mooyah, Uno Mas Cocina and Tequila, Verizon Wireless

Wednesday (4/6) thru Friday (4/8)
·         Remove existing concrete sidewalk adjacent to buildings
o   Temporary access will be provided at each business
·         Installation and grading of new aggregate base course
·         Installation of concrete forms for concrete sidewalk
·         Installation of reinforcement along buildings 

Week of April 11th 
·         Pour concrete sidewalk adjacent to buildings starting in late afternoon / early evening
·         Access to businesses will be coordinated individually

 On-street parking along Tower Drive will be limited, please utilize parking garages to the greatest extent possible.

Flaggers will be present along Tower Drive, please use caution and drive carefully.

All scheduled work is weather dependent. Every effort will be made to provide notifications due to schedule changes.