- Removed existing concrete sidewalk adjacent to building on the west side of Tower Drive from Aviator Lane to Valor Drive, and the north side of Sable Drive (Zone 1 and Zone 2).
- Installed temporary ramps to businesses.
- Graded and installed base course, set forms, installed reinforcement, and prepared for concrete pour.
- Late afternoon/early evening: concrete pouring.
- Businesses with two doorways, one doorway will be closed per day. Concrete pouring schedule for businesses with one doorway will be coordinated individually.
- Concrete walkways will be accessible to pedestrians by start of business the morning after the concrete pour.
- Starting Friday (4/15) we will begin removing existing sidewalk from the curb to the new sidewalk on the west side of Tower Drive from Aviator Lane to Valor Drive (Zone 1 and Zone 2).
All scheduled work is weather dependent. Every effort will be made to provide notifications if and when the schedule changes.