Concrete Sidewalk Removal and Replacement along Navy Blvd. Starts May 2nd

Work completed last week, April 25th to 29th:
·         Poured concrete sidewalk at various locations along the south side of Sable Drive and the west side of Tower Drive.
·         Completed concrete sidewalk removal from existing curb & gutter to newly installed sidewalk on west side of Tower Drive from Aviator Lane to Valor Drive.
·         Began concrete curb & gutter removal and replacement on the west side of Tower Drive from Aviator Lane to Wolverine Drive and along Tower Drive from Sable Drive to Valor Drive.
·         Installed temporary power for street lighting on the west side of Tower Drive from Aviator Lane to Valor Drive.
·         Began installing curbing for planter beds behind concrete curb & gutter.
·         Began installation of irrigation piping.

Work anticipated to be completed next week, beginning May 2:
·         Removal of existing concrete sidewalk adjacent to the buildings on the north and south side of Navy Boulevard from Tower Drive to Patriot Blvd.
o   Temporary access ramps will be provided at each door way.
·         Grade and install base course, set forms, install reinforcement, and prepare for concrete pour.
·         Pour concrete sidewalk adjacent to buildings along the north and south sides of Navy Blvd from Tower Drive to Patriot Blvd.
o   Concrete installation in front of businesses will be coordinated individually
·         Continue installation of electrical conduits for street lighting and tree accent lights.
·         Continue with installation of irrigation piping.

Looking ahead:
·         Once the electrical conduits and irrigation piping is installed on the west side of Tower Drive, the remaining concrete sidewalk and colored/stamped concrete will be poured.
·         Parking in garages is strongly encouraged as street parking on Tower Drive is limited.