Poured
concrete sidewalk at various locations along the south side of
Sable Drive and the west side of Tower Drive.
·
Completed
concrete sidewalk removal from existing curb & gutter to newly installed
sidewalk on west side of Tower Drive from Aviator Lane to Valor Drive.
·
Began
concrete curb & gutter removal and replacement on the west side of
Tower Drive from Aviator Lane to Wolverine Drive and along Tower Drive from
Sable Drive to Valor Drive.
·
Installed
temporary power for street lighting on the west side of Tower Drive from Aviator
Lane to Valor Drive.
·
Began installing curbing for planter beds behind
concrete curb & gutter.
·
Began installation of irrigation piping.
Work anticipated to be completed next week,
beginning May 2:
·
Removal of existing concrete sidewalk adjacent to the buildings on the north and south
side of Navy Boulevard from Tower Drive to Patriot Blvd.
o Temporary access ramps will be provided at
each door way.
·
Grade and install base course, set forms, install
reinforcement, and prepare for concrete pour.
·
Pour
concrete sidewalk adjacent to buildings along the north and south sides of Navy
Blvd from Tower Drive to Patriot Blvd.
o Concrete installation in front of businesses
will be coordinated individually
·
Continue
installation of electrical conduits for street lighting and tree accent lights.
·
Continue with installation of irrigation
piping.
Looking ahead:
·
Once
the electrical conduits and irrigation piping is installed on the west side of
Tower Drive, the remaining concrete sidewalk and colored/stamped concrete will be poured.
·
Parking
in garages is strongly encouraged as street parking on Tower Drive is limited.