Completed
concrete sidewalk removal adjacent to buildings on the north and south side of
Navy Boulevard.
·
The sidewalk was poured
adjacent the buildings along the north and south side of Navy Boulevard.
o
Locations in
front of doorways to businesses were skipped to be poured at a more convenient
time.
o
Temporary ramps installed
to provide access to businesses.
·
Began brick paver
removal along north and south side of Navy Boulevard.
·
Continued to
install electrical conduits for street lighting and tree accent lights and
irrigation piping on west side of Tower Drive from Aviator Lane to Valor
Drive.
o
Once the
electrical equipment is installed, the sidewalk from the curb & gutter to
the new sidewalk will be replaced.
Work anticipated to be completed next week, beginning
May 9:
·
Removal of
existing concrete sidewalk from existing curb & gutter to newly
installed sidewalk on north and south side of Navy Boulevard.
o
Grade and install
base course, set forms, install reinforcement, and prepare for concrete pour.
·
Removal of
ramp/staircase and sidewalk will begin on the north side of Aviator Lane from
Tower Drive to Patriot Boulevard.
o
During this time,
the sidewalk on the north side of Aviator Lane will be closed. Pedestrians will
be directed to use the sidewalk on the south side of Aviator Lane.
·
Continue
installation of electrical equipment.
Friendly Reminder:
·
All businesses
are open during construction!
·
Surface parking
spots are limited. Parking in garages is strongly encouraged.