Sidewalk removal on the east side of Tower Drive
from Valor Drive to Navy Blvd.
·
Prep and pour sidewalk adjacent to the buildings
on the east side of Tower Drive from Valor Drive to Navy Blvd
·
Prep and pour concrete sidewalk and driveways at
the following locations:
o
South side of Valor Drive east of Tower Drive
o
North side of Sable Drive
o
Tower Drive in front of Eggsperience
o
Tower Drive access to rear parking garage
·
Removed and poured required curb & gutter
along Tower Drive from Valor Drive to Navy Blvd.
·
Sealed previously installed stamped and colored
concrete
·
Install electrical conduit and lighting
accessories on the north side of Sable Drive
·
Install irrigation conduits on the north side of
Sable Drive
Construction
activity scheduled for next week, July 18th to July 22nd
·
Remove and replace vandalized concrete sidewalk
along Valor Drive and Tower Drive
·
Remove and replace driveways to parking garages
on north side of Sable Drive
·
Pour concrete curb & gutter along Tower
Drive
·
Remove remaining sidewalk along Valor Drive east
of Tower Drive
·
Excavate for planter beds
·
Install concrete curbing around planter beds on
Tower Drive and Valor Drive
·
Remove concrete sidewalk along north side of
Wolverine Drive
·
Install electrical conduit and lighting
accessories along Sable Drive, Wolverine Drive, Tower Drive, and Valor Drive
·
Install irrigation conduits along Sable Drive,
Wolverine Drive, Tower Drive, and Valor Drive
·
Begin installing irrigation piping and spray
heads along Tower Drive
Anticipated work in future weeks:
·
Week of July 25th
o
Pour remaining concrete sidewalk along Tower
Drive from Navy Blvd to Valor Drive
o
Pour remaining concrete sidewalk along Valor
Drive
o
Pour stamped and colored concrete along Valor
Drive and Tower Drive.
·
Prior to Arts Festival on August 5th
o
All concrete sidewalk previously removed will be
replaced along Tower Drive, Valor Drive, Sable Drive, and Wolverine Drive
·
Early September
o
Landscape restoration with new trees and
perennials in the planting beds.
o
Due to more favorable growing conditions
This past week had a few unfortunate circumstances that caused some significant issues for businesses throughout the project area. On Friday, July 15th, power was lost for an extended period of time for all businesses along the west side of Tower Drive. The exact cause for the power outage is still being determined. The major priority at this point is to get power restored as quickly as possible. We understand the major affect this had on all the businesses in the area and will continue to work to determine the cause for the outage.
Friendly
Reminder:
·
All businesses are open during construction!
·
Surface parking spots are limited. Parking in
garages is strongly encouraged.