Friday, July 8, 2016

Work along Tower Drive Between Navy Blvd. and Valor Drive Begins


Work completed this week, July 2nd  to July 9th  

·         Removed existing retaining wall on south side of Valor Drive east of Tower Drive
·         Installed new retaining wall on north side of Valor Drive east of Tower Drive
o   Businesses will be provided temporary access during construction. Thank you for your patience and understanding. We will continue to do everything possible to ensure access is provided throughout the day.
·         Concrete sidewalk removal along north side of Sable Drive
·         Concrete curb and gutter removal and replacement along the north side of Sable Drive

Construction activity scheduled for next week, July 11th to July 15th  

·         Sidewalk removal on the east side of Tower Drive from Valor Drive to Navy Blvd.
o   This will be the last significant stage of sidewalk removal along Tower Drive
·         Prep and pour sidewalk adjacent to the buildings on the east side of Tower Drive from Valor Drive to Navy Blvd
·         Late afternoon / early evening work, including concrete pouring, scheduled for Monday through Wednesday
·         Remove required curb & gutter along Tower Drive from Valor Drive to Navy Blvd.
·         Prep and pour concrete sidewalk on the south side of Valor Drive east of Tower Drive, the north side of Sable Drive and on Tower Drive in front of Eggsperience
·         Install electrical conduit and lighting accessories on the north side of Sable Drive
·         Install irrigation conduits on the north side of Sable Drive


Anticipated work in future weeks:

·         Week of July 18th
o   Removal and pouring of concrete sidewalk on the north and south side of Navy Blvd in front of Bravo and Jameson’s Steakhouse
o   Removal and pouring of concrete sidewalk on the south side of Wolverine Drive
o   Potentially pour sidewalk from sidewalk previously installed to curb & gutter
·         Early September
o   Landscape restoration with new trees and perennials in the planting beds
o   Due to more favorable growing conditions
 
Friendly Reminder:

·         All businesses are open during construction!
·         Surface parking spots are limited. Parking in garages is strongly encouraged.