Work
completed this week, July 2nd to July 9th
·
Removed existing retaining wall on south side of Valor Drive east of
Tower Drive
·
Installed new retaining wall on north side of Valor Drive east of Tower
Drive
o Businesses
will be provided temporary access during construction. Thank you for your
patience and understanding. We will continue to do everything possible to
ensure access is provided throughout the day.
·
Concrete sidewalk removal along north side of Sable Drive
·
Concrete curb and gutter removal and replacement along the north side of
Sable Drive
Construction activity scheduled for next week, July 11th to July 15th
·
Sidewalk removal on the east side of Tower Drive from Valor Drive to Navy Blvd.
o This will be the last significant stage of sidewalk removal along Tower Drive
·
Prep and pour sidewalk adjacent to the buildings on the east side of
Tower Drive from Valor Drive to Navy Blvd· Late afternoon / early evening work, including concrete pouring, scheduled for Monday through Wednesday
· Remove required curb & gutter along Tower Drive from Valor Drive to Navy Blvd.
· Prep and pour concrete sidewalk on the south side of Valor Drive east of Tower Drive, the north side of Sable Drive and on Tower Drive in front of Eggsperience
· Install electrical conduit and lighting accessories on the north side of Sable Drive
· Install irrigation conduits on the north side of Sable Drive
Anticipated work in future weeks:
·
Week of July 18th
o Removal
and pouring of concrete sidewalk on the north and south side of Navy Blvd in
front of Bravo and Jameson’s Steakhouse
o Removal
and pouring of concrete sidewalk on the south side of Wolverine Drive
o Potentially pour sidewalk from sidewalk previously installed to curb & gutter
·
Early September
o Landscape
restoration with new trees and perennials in the planting beds
o Due
to more favorable growing conditions
·
All businesses are open during construction!
·
Surface parking spots are limited. Parking in garages is strongly