Friday, July 22, 2016

Construction Continues on Tower Drive from Navy Blvd to Valor Drive

Work completed this week, July 18th to July
  • Removed and replaced vandalized concrete sidewalk along Valor Drive and Tower Drive
  • Removed and replaced driveways to parking garages on north side of Sable Drive
  • Poured concrete curb & gutter along Tower Drive
  • Removed remaining sidewalk along Valor Drive east of Tower Drive
  • Excavated for planter beds
  • Installed concrete curbing around planter beds on Tower Drive and Valor Drive
  • Removed concrete sidewalk along north side of Wolverine Drive
  • Installed electrical conduit and lighting accessories along Sable Drive, Wolverine Drive, Tower Drive, and Valor Drive
  • Installed irrigation conduits along Sable Drive, Wolverine Drive, Tower Drive, and Valor Drive
  • Began installing irrigation piping and spray heads along Tower Drive
Construction activity scheduled for next week, July 25th to July 29th  
  • Pour remaining concrete sidewalk along Tower Drive from Navy Blvd to Valor Drive
  • Pour remaining concrete sidewalk along Valor Drive
  • Pour stamped and colored concrete along Tower Drive and Valor Drive
  • Install irrigation conduits along Sable Drive, Wolverine Drive, Tower Drive, and Valor Drive
  • Install electrical conduit and lighting accessories along Sable Drive, Wolverine Drive, Tower Drive, and Valor Drive

Anticipated work in future weeks:
  • Prior to Arts Festival on August 5th
    • All concrete sidewalk previously removed will be replaced along Tower Drive, Valor Drive, Sable Drive, and Wolverine Drive
  • Early September
    • Landscape restoration with new trees and perennials in the planting beds - due to more favorable growing conditions
 